top of page
  • communication2418

MB Sewer Schedule Update

Mission Beach Water & Sewer Replacement

Hello Kerry,


Here is important information about the Mission Beach Water & Sewer Replacement project. Please share this information with others who you feel may have an interest in this update.


Temporary Water Shut-off Information


A planned water disruption will affect the following areas:


  • 807 - 833 Brighton Court

  • 808 - 839 Balboa Court

  • 2708 - 2786 Bayside Lane

  • 807 - 833 Capistrano Place

  • 810 - 833 Avalon Court

  • 802 - 836 San Luis Rey Place

  • 2700 - 2799 Mission Blvd.

Tuesday, Oct. 1

8 a.m. to 5 p.m.


About the Water Shut-off

  • Water service will not be available throughout the shut-off time; please plan accordingly, including putting water in containers ahead of the shut-off.

  • Access to homes and emergency vehicles will be maintained at all times.

How the Area will be Affected:

  • Temporary "No Parking" signs will be posted at least 72 hours before work begins. Vehicles in violation of signs will be towed.

  • Noise from construction equipment may be heard.

  • Temporary road closures, traffic rerouting, parking and access restrictions will be in effect during work hours.

  • Construction noise may be heard.

Contact Us

Call: 619-533-4207

Email: engineering@sandiego.gov

Website: sandiego.gov/cip


       

City of San Diego Engineering & Capital Projects Department | 525 B St. Suite 750 | San Diego, CA 92101-4905 US


Recent Posts

See All

Comments


bottom of page